Lebanon’s Litani River Authority reports 23,787,500 kWh of electricity production for October 2026 across the Abdel Aal, Arcache and Charles Helou plants. That equals 23.7875 GWh, rounded to 23.79 GWh on the cover. It is measured monthly output from these plants, not national generation or installed capacity.
Three plants, one monthly total
The official table records 5,269,000 kWh at Abdel Aal, 12,919,500 kWh at Arcache and 5,599,000 kWh at Charles Helou. These sum to the published total. The reporting period is 1–31 October; the document does not state its publication date.
A kWh measures energy delivered over time. A capacity figure in MW answers a different question: how much power equipment can produce at a moment under specified conditions. This table cannot be used as a new-capacity announcement or a commissioning notice.
Litani River Authority · 2026-11-20
Why this is not a household-hours calculation
Dividing the monthly total by an assumed household consumption would produce a hypothetical equivalent, not a count of homes actually supplied. The report does not allocate these units to particular customers, neighbourhoods or hours of network availability.
A building owner still needs evidence about the local connection and actual service pattern. The output figure alone cannot determine whether backup equipment is unnecessary, or establish a household’s bill saving.
Litani River Authority · 2026-11-20
How to use the next report
Track the same plants and units over comparable periods. Before describing a change as an efficiency gain, examine operating days, water conditions and any interruptions; a monthly total by itself cannot identify the cause.
Hydropower is renewable generation, but this operational table does not provide a lifecycle emissions assessment, new-project financing terms or a tariff. Its value is narrower and useful: a transparent account of electricity actually produced by an existing Lebanese hydroelectric system.
Litani River Authority · 2026-11-20
Related reading
Solar for 12 Lebanese vocational schools: the handover questions that matter
Prepared and reviewed 20 November 2026. Source dates and project stages are stated in the article; practical questions are editorial analysis.
Sources
- Monthly hydroelectric production, October 2026
Litani River Authority · Accessed: 2026-11-20
1–31 October 2026 · Three LRA hydroelectric plants; not all Lebanese electricity