Government spokesman Konstantinos Letymbiotis said on 17 November 2026 that the procedure to disburse €25 million for the Great Sea Interconnector (GSI) has begun, adding that it is subject to regulatory decisions and will take time to complete. The GSI is the planned subsea power cable that would connect Cyprus’s electricity grid, today isolated, to Greece via Crete. This is the first payment under a September 2024 memorandum between the two governments that caps Cyprus’s contribution at €125 million.
How the money is meant to move
According to Cyprus Mail, citing government sources and the Cyprus News Agency, the state will credit the funds to Cyprus’s Transmission System Operator. The operator will then seek written approval from the energy regulator, described by the sources as a formality, before transferring the €25 million to Admie, Greece’s independent power transmission operator and the project’s promoter.
The memorandum sets €25 million a year for 2025 to 2029, up to €125 million in total. Sources told the newspaper the total would not change even if completion slips beyond 2030. President Nikos Christodoulides had said in September that Cyprus would pay once a navigational notice (Navtex) was issued for the seabed surveys. Greek authorities issued it on 6 November at the request of Nexans, the French cable maker; the survey vessel left Heraklion on 10 November and work began on 12 November in international waters east of Karpathos.
Cyprus Mail (Elias Hazou), citing government sources and the Cyprus News Agency · 2026-11-17
Who pays, and when
The annual €25 million comes from the state budget, so taxpayers rather than electricity bills fund it for now. Energy Minister Michalis Damianos told a parliamentary committee in October that households would pay nothing through their bills until the interconnector is completed and electricity reaches Cyprus, and that those costs would then be recovered over 30 years. He also said that if electricity does not reach Cyprus, Cyprus will not pay.
The amounts claimed are larger than the payment. Admie has submitted €302 million in expenditure, of which Cyprus’s energy regulator had recognised €82 million, according to the same report. The project has been allocated €650 million in European funding, and a European Investment Bank study is under way.
To Vima (English edition) · 2026-10-20
The timetable now points to end-2031
Admie’s 2027–2036 development plan, as reported by Greek broadcaster ERT on 14 November, puts completion of the Greece–Cyprus section at the end of 2031, later than the 2030 originally indicated. The plan says about 60% of the required seabed surveys are complete and a contractor has been selected for the converter stations, which turn the cable’s direct current into the alternating current used on each grid. Cyprus will need a new converter station; the Damasta station on Crete will be expanded.
A study by the Aristotle University of Thessaloniki estimated annual savings of €123 million to €138 million, or 19% lower energy prices for Cypriot consumers. That is a model estimate, not a measured result or a promised tariff.
Cyprus Mail (Tom Cleaver), citing ERT report on Admie's 2027–2036 development plan · 2026-11-14
What it means for homes and businesses
Nothing changes on a household or shop bill because of this payment. The practical value of the cable, if built, is connection: an isolated grid cannot send surplus daytime electricity elsewhere or import power when local plants are short. The cable itself is not a source of energy, renewable or otherwise; it carries whatever electricity is produced on either side.
Still uncertain: whether the regulator’s written approval follows quickly, whether the surveys finish without interruption (Turkey says the route crosses its waters, which Cyprus and Greece reject), how the remaining cost is financed, and whether the end-2031 date holds. Businesses planning energy-intensive premises in Cyprus should budget on current tariffs and local options such as rooftop solar, not on the interconnector.
Related reading: Nicosia’s wastewater solar project: connected power and expected output are different.
Cyprus Mail (Elias Hazou), citing government sources and the Cyprus News Agency · 2026-11-17
Prepared and reviewed 18 November 2026. Source dates and project stages are stated in the article; practical questions are editorial analysis.
Sources
- Process begins to release €25m for GSI
Cyprus Mail (Elias Hazou), citing government sources and the Cyprus News Agency · Published: 2026-11-17 · Accessed: 2026-11-18
September 2024 memorandum; payments 2025–2029; surveys November 2026 · Cyprus state contribution to the Great Sea Interconnector
- Greece-Cyprus interconnector to be complete by end of 2031, Admie says
Cyprus Mail (Tom Cleaver), citing ERT report on Admie's 2027–2036 development plan · Published: 2026-11-14 · Accessed: 2026-11-18
Admie development plan 2027–2036 · Greece–Cyprus section of the GSI
- Cyprus links €25 million GSI payment to Greek sea surveys
To Vima (English edition) · Published: 2026-10-20 · Accessed: 2026-11-18
October 2026 budget hearing · Cyprus energy ministry statements on GSI financing